Thursday, November 5, 2026
Home
Commission
Officers
Committee
Annual Reports
Tenders
Right To Information
Contact Us
Regulations
Orders
Tariff Orders
Orders u/s 142
Notices
Schedule of Hearings
Record of Procedings
Draft-Regulations
Repealed
Licenses
Procedures/Agreements
Supply Code
Cost Data Book
Other Documents
Electricity Ombudsman
Vacancy
Policies
UP Govt Policies
Rules
Guidelines
CEA Regulation (Technical)
Information-4(1)(b) RTI
Expert Committee Reports
Tariff Filing Portal (For Licensees)
Tariff Dashboard
PVVNLMVVNLPuVVNLDVVNLKESCONPCL
PVVNLMVVNLPuVVNLDVVNLKESCONPCL
User Login
 
 
 
 
 
 
                 What's New  
Sr. NoDocument Name   
1Order dated 29/10/26 for -2409 of 2026 - UPPCL. - Seeking clarification regarding the applicability and continuation of tariff adjustment/deduction on account of utilization of existing transmission infrastructure for evacuation of power from additional generating capacity commissioned under supplementary power purchase agreements in light of the Uttar Pradesh electricity regulatory commission (captive and renewable energy generating plants) regulations, 2024.Pt-no-2409of2026DCMSriramLtd--29-10-2026-PDF1029202651509PM.pdf2 
2Order dated 29/10/26 for 2426 of 2026 - Rosa Power Supply Company Ltd. - Seeking declaration of Change in Law and consequential compensation for additional expenditures.P-no-2426of2026-PDF1030202653633PM.pdf2 
3Order dated 29/10/26 for 2267 of 2025 Powergrid Meerut Simbhaoli Transmission Ltd.- Change in Law.Orderdarted29-10-2026(2267of2025)-PDF1030202651259PM.pdf2 
4Order dated 29/10/26 for 2067of 2024 - Shree Cement - Direct the respondent to pay the balance amount of Rs. 23,45,594 to the petitioner with along with the late payment surcharge in term of the contract from the date of order till the date of payment.Orderdated29-10-2026(2067of2024)-PDF1030202651149PM.pdf2 
5Order dated 29/10/26 for 2134 of 2024 - Powergrid Gomti Yamuna Transmission Limited vs UPPCL and ors - Relief under Force Majeure (Article 11) and Change in Law (Article 12) of Transmission Service Agreement dated 09.07.2021, related to ‘construction of 400/220/132 kV GIS substation, Mohanlal Ganj (Lucknow) with associated 400 kV lines, and other 765 kV & 400 kV LILO lines at 765 kV GIS Substation Rampur and 400 kV LILO (Quad moose on Monopole) at 400 kV GIS Substation Sector 123 Noida implemented by PowerGrid Gomti Yamuna Transmission Limited.Orderdated29-10-2026(2134of2024)-PDF1030202651001PM.pdf2 
6Order dated 29/10/26 for - 2339 of 2025 - UPRVUNL – Parichha Ext. Stage II. - Submission of MYT petition for Approval of ARR and Determination of Tariff for FY 2024-25 to FY 2028-29 in respect Parichha Ext. Stage II (2 X250 MW) TPS.Pt-no-2239of2025-UPRVUNL-29-10-2026-PDF1029202651200PM.pdf2 
7Order dated 29/10/26 for -2235 of 2025 -UPRVUNL – Parichha Ext. - Submission of MYT petition for Approva of ARR and Determination of Tariff for FY 2024-25 to FY 2028-29 in respect of Parichha Ext. (2 X210 MW) TPS.Pt-no-2235of2025-UPRVUNL-29-10-2026-PDF1029202650924PM.pdf2 
8Order dated 29/10/26 for - 2234 of 2025 - UPRVUNL – Anpara ‘B’ - Submission of MYT petition for Approve of ARR and Determination of Tariff for FY 2024-25 to FY 2028-29 in respect of Anpara “B’ (2 X 500 MW) TPS.Pt-no-2234of2025-UPRVUNL-29-10-2026-PDF1029202650827PM.pdf2 
9Order dated 29/10/26 for 1328 of 2018 & 1328 - IA1/2026 - Petition regarding instructions to UPPTCL to release tariff payments due since August 2017 after commissioning of entire Group -1/COD-1 elements as per clause 6.2 of transmission service agreement dated 20.01.2012/ supplementary agreement dated 09/06/2018. Orderdated29-10-2026inPetitionNo-1328of2018-pdf1029202645516PM.pdf2 
10Order dated 29/10/26 for 2129 of 2024 - Powergrid Rampur Sambhal Transmission Ltd. vs UPPCL and ors - Relief under force Majeure (Article11) and Change in Law, (Article 12) of Transmission Service Agreement dated 07.08.20219, related to construction of 765/400/220 KV GIS Substation, Rampur and 400/220/132 KV GIS Substation, Sambhal along with associated Transmission Lines by Powergrid Rampur Sambhal Transmission ltd.Orderdated29-10-2026(2129of2024)-pdf1029202645215PM.pdf2 
11Order dated 29/10/26 for 2264 of 2025 - Meerut Shamli Power Transmission Limited - Seeking appropriate relief with regard to extension of scheduled commissioning date and stay off any coercive measures.Orderdated29-10-2026(2264of2025)-pdf1029202645121PM.pdf2 
12Order dated 29/10/26 for 2359 of 2026 - Seeking appropriate reliefs with regard extension of scheduled commissioning date and stay off any coercive measures.Orderdated29-10-2026(2359of2026)-pdf1029202645052PM.pdf2 
13Order dated 28/10/26 for 2367 of 2026 Seeking reimbursement of Excess Energy Charges paid to PPGCL along with carrying costs.P-no-2367of2026-pdf1029202643825PM.pdf2 
14Order dated 28/10/26 for 2213 of 2025 - UPPCL - Approval for tender documents including the request for Qualification, Request for Proposal and Draft PPA to be floated by UPPCL for Procurement of 1000 MW of source Agnostic Peak Power for medium Term.P-No-2213of2025-pdf1029202643546PM.pdf2 
15Order dated 28/10/26 for 2340 of 2026 Seeking issuance of directions to respondents to permit repowering/replacement of degraded solar PV modules for the petitioner’s 1 MW Solar Power Project, further, the petition is also being filed seeking a declaration that denial of consent for repowering/replacement of decfective/demaged modules of the project vide letter dated 09.10.2025 issued by respondent no. 1, is unlawful, in view of the provision of PPA ad applicable regulation and MNRE guidelines for repowering of solar modules, consequently, the petition is also seeking compensation toward generation losses incurred by the petitioner for the period from 16.12.2024 till 15.12.2025 amounting to Rs. 1.438 Crores.P-no-2340of2026-pdf1029202643657PM.pdf2 
12345678910...
 
Chairman's Desk
Total Hits
13587945
Home  |  Picture Gallery  | SiteMap  |  Contact Us
Disclaimer: While every care has been taken to ensure the accuracy of information furnished in this website, UPERC does not accept any responsibility or liability for any damage or loss to any person / institution / organization for the result of any action taken on the basis of this information. However, UPERC shall be obliged if errors / omissions are brought to its notice for carrying out corrections in the next update.
 Design By: WizTech Consultancy      "Best viewed on IE.7 and above at 1024x768 resolution"