Order
by the Commission on obligation
of M/s Baidyanath Enterprises Ltd. regarding its payment of Minimum Consumption
Guarantee to UP Power Corporation Ltd.
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSIONLUCKNOW. Petition No: Present: 1.
Shri J.L. Bajaj, Chairman 2.
Shri S.C. Dhingra, Member 3.
Shri Arun Sarkar, Member In
the matter of: Obligation
of M/s Baidyanath enterprises Ltd. regarding its payment of Minimum Consumption
Guarantee to UP Power Corporation Ltd. And In
the Matter of: UP
Power Corporation Ltd through Executive Engineer, Electricity Distribution
Division-1, Civil Lines, Jhansi. ------Appellant
And 1.
M/s Baidyanath Enterprises, 172, Gusainpura, Jhansi 2.
The Director, Electrical Safety, Gomti Nagar, Lucknow. ----Respondents
ORDER
(a)
Whether the Electrical Inspector had jurisdiction to adjudicate regarding
the technical capability of the Electrical System under Clause VI (3) of the
schedule? If no, what are its implications? (b)
Whether the appellant company fulfilled its part of the contract to make
available the supply to the respondent? (c)
Whether MCG charges are
payable by the respondent? Our findings on these issues are given in subsequent
paragraphs.
Jurisdiction
of Electrical Inspector under Clause VI(3) of the Schedule
7.
The clause VI (3) of the Schedule is reproduced below: “Where any difference or dispute arises as to the amount of energy
to be taken or guaranteed as aforesaid, or as to the cost of any
service-line or as to the sufficiency of the security offered by any owner or
occupier (or as to the position of the meter board) or as to the improper use of
energy, or as to any alleged defect in any wires, fittings, works or apparatus,
or as to the amount of the expenses incurred under the third proviso to
sub-clause (1), the matter shall be referred to an Electrical Inspector and then
decided by him.” 8.
The reference “amount of energy to be taken or guaranteed as
aforesaid” in this clause is to the subsection (a) of the first proviso to
clause VI (1) of the Schedule. As per the scheme of Clause VI, the distribution
licensee is obliged to supply electricity to owners or occupier living in the
vicinity of any area where distribution main has been constructed. However the
first proviso lays down that before such supply is given, the consumer has to
execute an agreement with sufficient security binding himself to take the supply
of energy for a period not less than two years of such amount of energy as will
assure to the licensee, at the current rates charged by him, an annual revenue
not exceeding 15% of the cost of the service line. It is in this context that
the clause VI (3) of the Schedule provides that if there is a dispute as to the
sufficiency of the security so required under clause VI(1) of the Schedule or
the minimum amount of energy to be taken or guaranteed then such dispute shall
be referred to the adjudication of the electrical Inspector. The key issue here
is that the dispute that may be referred to the Electrical Inspector, and one
that he may decide, is regarding the quantum of security demanded by the
licensee and the minimum amount of consumption of energy that is to be
guaranteed by the consumer to meet the revenue requirement of the licensee.
There is no reference in clause VI (3) of the Schedule whereby Electrical
Inspector can adjudicate whether the licensee’s electrical system feeding the
consumer’s premises was capable or not of supplying the contracted load.
Obviously, such a dispute would arise before the agreement is signed and the
load is released. It is undisputed that in the instant case an agreement had
already been entered into between the appellant and the respondent and the
system had been energized in the premises of the respondent in his presence. In
view of this clear provision of law we conclude that the Electrical Inspector
exceeded his jurisdiction in determining the technical capability of the feeder
and the impugned order is liable to be set-aside on this ground alone. The first
issue is accordingly decided. 9.
Having decided the jurisdictional issue as above, the Commission
deliberated whether it is for the Commission to adjudicate upon dispute between
a licensee and its consumers where the avenues of redressal have not been
established. A reference to the provisions of the Electricity Reforms Act, 1999
is in order. It is noted that section 10(k) of the Act enjoins upon the
Commission to “ensure a fair deal to the consumers”. Further, section 34 of
the said Act authorizes the Commission to arbitrate in disputes between the
licensee and the consumers arising out of the regulations regarding consumer
rights prescribed under section 30(1) of the Act. Thus, there is no legal bar on
the Commission in adjudicating upon disputes between the licensee and its
consumers. However, in the matter of consumer grievances the Commission would
like to define its role as one of a watchdog to ensure that the systems for
dealing with the consumer grievances are laid down and adhered to rather than to
adjudicate on each grievance. Thus, a consumer may approach the Commission only
after the process within the licensee system is exhausted and not otherwise. 10. In the instant case although this process has not been followed, the Commission is of the view that it is a fit case for the intervention of the Commission as the dispute is continuing since long and in different fora. The licensee has already taken a stand in the matter and now it is unrealistic to presume that the respondent would get a fair hearing if the dispute is referred back to the licensee. In these circumstances the Commission has proceeded further with the matter. Whether
the Supply was made available to the respondent as per the agreement? 11.
It is undisputed that the line was extended up to the premises of the
respondent and the meter was installed. It
is the case of the respondent that the spinning mill feeder was overloaded and
therefore incapable of meeting the contracted demand.
On the other hand, the appellant’s case is that the spinning mill
feeder was capable to deliver the contracted load and it was the respondent who
failed to install its plant and machinery. The question of inadequacy of the
feeder could arise only after the load was connected. In the absence of
connected load, the respondent’s case is based upon a hypothesis and cannot be
relied up on. 12.
The key issues involved here are (i) whether the feeder was capable of
supplying the contracted load and (ii) whether conclusion regarding the fact of
supply may be reached with reference to the theoretical computation of the line
capability or on the basis of failure in actual supply? 13. It
is evident from the record that the respondent did not install its plant and
machinery because of some technical problem that had nothing to do with the
appellant. This is brought out
clearly in the letters of respondent dated 10-7-97 and 1-8-97 to the Chief
Engineer (Commercial) and the Chief Minister of the State respectively. The
relevant extracts are given below: “Since our plant is imported, consisting of Machinery from Germany and
Italy, we are undergoing major modifications. There are complex technical
difficulties arising out of the fact that this plant is based on 200V, 60 Hz.
There are major electronic control devices incorporated in it. If we run the
plant on 50 Hz, we lose up to 25 % in motor efficiency. Since it is well known,
that Spinning Unit have to work at over 95 % efficiency level in order to be
profitable, therefore, without complete overhaul of motors, pulleys, gears and
electronic devices we are unable to run our unit. We, very humbly request you to kindly allow temporary suspension of our
connection for a period of 5 to 6 months. We need this time to import certain
parts and to replace them in our unit. …Since you are aware that to import
equipment we need at least 3 months of shipping time-------We assure you that we
will not use your power during this period and meter reading will remain
same”. 14.
It is noted that this letter was written on 1/08/97 while respondent has
made out a case that he had been writing to the appellant since April’97 that
the feeder capacity was inadequate. This fact has not been denied by the
respondent and it proves that as of August’ 97 the plant of the respondent was
not installed. When even the plant was not installed it is farcical for
respondent to claim that adequate supply was not available. 15.
The respondent has taken another plea to establish that the supply was
not available by submitting that had it been the case, the transformer would
have recorded at least “No load losses” even if his plant and machinery were
not available. The argument of the respondent does not seem to be correct, as he
himself was responsible for the operation and maintenance of 33 KV isolator. The
effect of transformer charging could have reflected on the 33 KV meter only if
the isolator was closed, which was an operation to be carried by the respondent
himself. Further, taking cognizance of the fact that the circuit CT installed at
the 33 KV metering apparatus was having a CT ratio of 150/1 with a multiplying
factor of 150, we agree with the submission of the appellant that it was almost
improbable for the meter to record any change as the meter would have recorded
one unit against an actual consumption of 150 units, which was not possible with
the transformer heating alone. 16.
In view of the above facts we come to the conclusion that the line was
installed up to the factory premises of the respondent and it was up to the
respondent to utilize the supply. In our opinion whether supply was available or not has to be
determined with reference to actual fact of the respondent having been unable to
run its plant due to lack of supply. In the absence of any connecting load,
which was clearly the responsibility of the respondent, the respondent cannot
complain about the inadequacy of supply. 17.
Even though our view is clear that it is for the consumer to establish
that it was unable to run its connected load due to inadequate supply and that
such issues cannot be decided on the basis of a theoretical consideration of the
system capability, we have nonetheless examined the issue of the technical
capability as raised by the respondent. The
respondent has contended that a load of 315 Amp was already connected to the
concerned feeder before the load was sanctioned to him. Thus, total load on the
feeder would have been 367.5 amp if their load was also connected to the feeder.
They have argued that the DOG (ACSR) conductors, which were used for supplying
the electricity, were incapable of carrying current in excess of 300 Amp. It is,
therefore, their case that the spinning mill feeder could not have supplied them
the contracted load. They have also
argued that the fact of technical incapability of the feeder is corroborated by
the admission of the officers of the appellant company made while sanctioning
the load that proper supply could be given only after a new feeder is
constructed between 132 kV substation Hansari and 33kV substation Nanadanpur and
subsequent steps taken by the appellant to initiate a project for construction
of a new feeder. 18.
The current carrying capacity of the DOG (ACSR) conductor is at the
center of the dispute. The commission verified the same from various sources
like Central Electricity Authority and few manufacturers’ manual and found out
that the current carrying capacity of the said conductor is 320 amps at 40
degree C. The maximum operating
load, achieved on the said feeder during the entire disputed duration (from
31-3-97 to 26-10-97), was 250 amps. Even if the load of M/s Baidyanath is added
to the feeder and it is assumed that M/s Baidyanath would have utilized up to
its full load capacity, the load on the feeder would have been, at the most, 303
amps, which is less than the current carrying capacity of the Dog ACSR conductor
i.e. 320 amps at 40 degree C. The Commission, therefore, does not agree with the
respondent that the total load on the feeder was higher than the current
carrying capacity of the Dog conductor. Further, appellant has been able to show
that above feeder has successfully carried a load of 360 amps in the month of
July 2001, which proves that there was hardly any problem with the current
carrying capacity of the conductor. The
Commission also does not agree with the calculation of the respondent regarding
various technical parameters such as MW-KM and VR. Even if
we consider the load on the conductor as the maximum operating load i.e. 300
amps, the corresponding voltage regulation at M/s Baidyanath Enterprises Limited
would have been 8.77%. This figure of voltage regulation has been arrived at
taking the distances, of 132 KV S/s Hansari to 33 KV S/s Nandan pur - 9 Kms, 33
KV S/s Nandan pur to 33 KV S/s Spinning Mill - 5 Kms and 33 KV S/s Spinning Mill
to the S/s of M/s Baidyanath Enterprises-0.45 Km, as submitted by the appellant.
The voltage regulation, so calculated, is less than the statutory 9% as given in
the Rule 54 of the Indian Electricity Rules, 1956. The Commission further agrees
with the appellant that any voltage drop, at the M/s Baidyanath Enterprises end
could have been compensated within the permissible limits by using the Tap
Changer available at the transformer. Again, MW-KM parameter is a direct
function of voltage regulation therefore, if percentage voltage regulation is
within the permissible limit, there is no question of the said parameter
exceeding the permissible limit. 19.
In view of the fact that ambient temperature has a direct impact on the
current carrying capacity of the feeder, the Commission, in its hearing dated
4-7-2001, directed both the parties to furnish the temperature profile of
Bundelkhand region and vintage of the Spinning Mill feeder. As far as
temperature profile of Bundelkhand region is concerned, appellant submitted a
monthly average temperature chart of Jhansi region for various months of year
2000 showing monthly average maximum temperature, monthly average minimum
temperature and average of maximum and minimum temperature. In response to this,
the respondent submitted the daily temperature chart of Jhansi indicating
maximum temperature on each day for the various months of year 1996, 1997, 1998
& 1999. It is noted that the maximum temperature in the Bundelkhand region
exceeds 40 degree C and on certain days goes up to 45 degree C in the months of
May and June and at this temperature the current carrying capacity of Dog ACSR
conductor may reduce to 250-255 amp. However, there are two issues involved
here. Firstly, this would happen only if the temperature and load peak at
the same time. However, the Commission has noted that a feeder like the one in
dispute achieves its electrical load peak between 6 to 10 pm, (which is also
recognized as peak hours during the summer) while the temperature peak occurs at
around 1:00 pm to 2:00 pm, when load of any mixed feeder during the summer
reduces by at least 40%. Therefore, it is not proved that the feeder could not
have supplied the contracted load. Secondly the average temperature even
during May and June was between 30 and 35 degrees and at these temperatures the
current carrying capacity of the Dog Conductor is 340 amps, which is much more
than the connected load including that of the respondent. The capacity during
remaining month should not be in question as even the maximum temperature in
those months is much less than 40 degree C. On the basis of the above analysis
the Commission concludes that the electric system was capable to supply the
contracted load to the respondent within the prescribed tolerances. 20.
Another argument offered by the respondent is that the appellant company
had itself proposed to construct a new feeder and this showed that the existing
feeder was incapable of meeting the contracted demand.
Respondent has relied upon several letters written by the officers of the
appellant company and has also referred the sanction order for construction of a
new feeder. This has not been denied by the appellant. However, the appellant
has argued that system up-gradation is a continuous exercise and this is done to
plan for future increases in demand. However, it does not prove that the
appellant failed to supply power to respondent as per agreement. Respondent has
also relied upon the judgments in N.I.I & S.Co. Vs. State of Haryana (1976),
M/s Raymond Vs. MPEB and M/s Dhanwat Rice and Oil Mills Vs. Bihar SEB (1989).
In these cases it has been held that if the supplier fails to meet the
contractual supply, it would be bound to make appropriate reduction in the MCG.
However, we do not agree that the facts of the present case are similar
to these cases. In the present case it is undisputed that the respondent did not
connect its load to the system and therefore question of supplier failing to
meet the requirement of contracted quantity of the supply could not have arisen.
On this ground also the respondent has failed to prove that the appellant did
not meet its contractual obligations. Whether
the respondent is liable to pay the MCG charges? 21.
In view of the fact that the respondent has failed to prove that the
appellant failed to supply electricity as per agreement, it remains liable to
pay the MCG charges as per rules. 22.
The Appeal is, accordingly, allowed. The order dated 14-3-2000 of the
Electrical inspector is set aside and the respondent is directed to pay the MCG
charges to the licensee as per rules. However, in view of the fact that it is
the respondent who had incurred the major cost for laying the line and it has
already suffered on account of this in fructuous investment, the appellant would
consider sympathetically the request of the respondent, if any made, for
reduction /remission of these charges, if permissible, under rules. (Arun
Sarkar)
(SC Dhingra)
(J L Bajaj)
Member
Member
Chairman Place: Lucknow Date: 30th
October 2001
|
UPERC, IInd Floor, Kisan Mandi Bhawan, Gomti Nagar, Vibhuti Khand, Lucknow-226010 Email: [email protected]
|