Amendment in Practice Directions for Captive Power Generation
|
UP
Electricity Regulatory Commission Notification
No.
1/2002
Date:
3 January 2002
Amendment
No.1 to the “Practice Directions for Captive Power Generations”,
adopted by the Commission in July, 2000. The
Practice Directions for Captive Power Generations (hereinafter referred as
Directions) were adopted by the Commission in July, 2000. In order to
further simplify the procedure, following amendments to the Directions are
being made in exercise of the powers of the Commission as given in clause
1.6 of the Directions, after considering the views of the UP Power
Corporation Ltd and Noida Power Company Limited. Kanpur Electricity Supply
Company did not give any comments on the proposed amendments. These
amendments will be applicable in the State of Uttar Pradesh only. Amendments I The
Clause 3.1 to 3.5 of the Directions shall be replaced by the following: 3.1
Applications
seeking consent for setting up new Captive units or for enhancement of
existing capacity should be filed in triplicate to UPERC, in the
prescribed form, along with an affidavit, as prescribed in the Business
Regulation, 2000 of the Commission. The form may be obtained free of cost
from the office of UPERC or may be down loaded from its website at www.uperc.org. 3.2
A
processing fee of Rs 2500 for capacity up to 1 (one) MW and Rs 5000 for
capacity in excess of 1 (one) MW is also to be deposited by way of draft
or pay order. 3.3
The
CPP owners, permitted to sell electricity, shall pay an annual fee as
prescribed in Regulation 5 and 6 of the UPERC (Fees and Fines) Regulation,
2000, amended from time to time. At present the fee is payable at the rate
of Rs.10, 000 per 10 MW or part thereof. 3.4
Automatic
Consent:
Following
cases will be covered under “Automatic Consent” route, provided
capacity requested is not more than 25 MW and proposal does not involve
any sale of energy: (a)
Standby units for a capacity up to 1.25 times the contracted load
with Licensee. (b)
Bagasse based captive sets based on co-generation in sugar mills
and (c)
HSD based captive sets in Sugar mills for starting of co-generation
units and for meeting the off-season load up to ¼ the capacity of the
co-generation unit. In
these cases, consent will be granted within seven working days of the
receipt of application complete in all respects. 3.5
Cases
other than those covered under Automatic Consent:
3.5.1
Two
copies of the application, along with processing fee if any prescribed by
the licensee, would be filed by the applicant with the licensee at the
same time as the application is filed with UPERC. The Licensee should send
his comments, if any, to UPERC within 45 days of the receipt of the
application, failing which the UPERC will proceed to decide the matter
presuming that the licensee has no objection to the grant of consent.
UPERC may, at its discretion, grant additional time to the Licensee upon
his request. 3.5.2
UPERC
shall generally decide the application within 30 days of receipt of the
views of the licensee and receipt of all information and documents from
the applicant. The procedure to be followed by UPERC for disposal of these
applications will be as laid down in its Business Regulations 2000 for
disposal of petitions. II
The clause 4.4 of the Directions would be replaced by the following: 4.4
The
maximum capacity permitted for standby CPP will be equal to 1.25 times the
contracted load with the licensee. By
the order of the Commission (Rajeev
Kapoor)
Secretary Lucknow Date: 3rd January 2002 |
UPERC, IInd Floor, Kisan Mandi Bhawan, Gomti Nagar, Vibhuti Khand, Lucknow-226010 Email: secretary@uperc.org
|